Skip to content
EARTHVOQ

Cut and fill calculator

Grid the site, enter both surfaces, see what moves and where.

[ 1 · Site ]

ft

ft

[ 2 · Surfaces ]

ft

The average of the ground as it is now, on your datum.

ft

Finished grade for the pad.

One average gives one depth, so Quick returns cut or fill, never both. A site with high and low ground needs Grid.

[ 3 · Earth movement ]

200′ × 150′

Enter the existing and proposed elevations. The section draws as you type.

Cut — material leavesFill — material arrives

[ 4 · Quantities ]

Cut

both elevations at four corners

Fill

both elevations at four corners

Net export

a computed cut and fill

Export, as hauled
Needs a swell factor
Bank volume the fill consumes
Needs a shrinkage factor
Truck loads
Needs swell and a truck capacity
Weight
Needs a loose density

The grid method approximates: it assumes the ground runs straight between nodes, so it cannot see a swale or a ridge that falls between them, and it is not a surface-to-surface computation. A tighter grid is what makes it better.

How this is calculated

The site is divided into a rectangular grid. At every node the existing elevation and the proposed elevation are recorded, and their difference is the depth of cut — positive — or fill — negative — at that point.

Each cell sits between four nodes. Its volume is the average of its four corner depths times its plan area, which is the average-end-area method applied in two directions. Cut and fill are accumulated separately across the site, so a cut cell never cancels a fill cell: that material still has to be dug, moved and placed.

A node with either elevation missing makes its cells unusable, and those cells are skipped rather than treated as flat ground. Assuming a blank elevation is zero would invent level terrain and understate the job.

Depth at a node

existing elevation − proposed elevation

Positive is cut, negative is fill. Both surfaces must be known at the node.

Cell area

spacing across × spacing down

Cells sit between nodes, so a 5 × 5 grid of nodes gives 4 × 4 cells.

Cell volume

mean of four corner depths × cell area ÷ 27

Average end area, in two directions. Divided by 27 for cubic yards.

Net

total cut − total fill

Positive means material leaves the site; negative means it has to be brought in. Both are bank volumes.

Export as hauled

net bank volume × (1 + swell)

What actually rides in the truck. Needs a swell factor for your material.

Bank volume the fill consumes

compacted fill ÷ (1 − shrinkage)

A cubic yard of cut does not make a cubic yard of compacted fill. Needs a shrinkage factor.

What it does not know

  • The grid method approximates. It assumes the ground varies evenly between nodes, so a swale or ridge falling between them is invisible to it, and it cannot represent a breakline at all. Tighten the grid where the ground moves.
  • A cell whose corners straddle grade averages its cut against its fill, so both are understated there. The calculator counts those cells and tells you how many — the fix is a tighter grid across the daylight line, not a different formula.
  • This is not a surface-to-surface computation and does not claim to be one. Contour or triangulated-surface takeoff is a different method with different data requirements.
  • The results are bank volumes. Loose volume for hauling and compacted volume for fill need swell and shrinkage factors for your material, which you supply.
  • Topsoil stripping, subgrade preparation and over-excavation are separate quantities not included here.