Trench volume with sloped or vertical walls, drawn as you type.

At the invert

Optional

Leave blank for vertical walls

Accepts 5' 6" or 5.5

Material and trucksUnlocks loose volume, weight and loads
Optional

Unlocks loose volume

Optional

Unlocks weight in tons

Optional

Unlocks truck loads

We do not fill these in. Swell and density depend on your material, its moisture and how it is dug — a borrowed average is how a haul budget goes wrong.

TOP BOTTOM EXISTING GRADE
Enter a bottom width and a depth to draw the section.

Trench excavation — bank

Enter the trench dimensions to see the volume.

3 more values:

  • Length
  • Bottom width
  • Depth
Cross-sectional area
Bank volume
Loose volume

Needs a swell factor for your material

Estimated weight

Needs a loose density

Truck loads

Needs swell and a truck capacity

Metric

How this is calculated

A trench is priced from its cross-section. With sloped walls that section is a trapezoid — wider at grade than at the invert — and its area is the mean of the two widths times the depth. Multiplying by the run gives the volume.

Leaving the top width blank collapses the trapezoid to a rectangle, which is exactly what a shored or competent-rock trench with vertical walls is. The calculator does not invent a slope you did not specify.

Cross-sectional area

((bottom width + top width) ÷ 2) × depth

The trapezoid. With equal widths it reduces to width × depth.

Bank volume

cross-sectional area × length

In-situ material — what a survey measures, not what fits in a truck.

Cubic yards

cubic feet ÷ 27

Exactly 27. A cubic yard is three feet cubed, by definition.

Side slope

(top width − bottom width) ÷ 2 ÷ depth

Reported as run:rise, the way it is called out on a plan. A 1.5:1 slope runs 1.5 ft out for every foot of depth.

Loose volume

bank volume × (1 + swell)

Only calculated once you give a swell factor for the material you are digging.

Truck loads

⌈loose volume ÷ truck capacity⌉

Rounded up. If you also give a density and a payload limit, the binding constraint wins and the calculator says which one it was.

What it does not know

  • It measures the trench you describe, not the one the ground gives you. Rock, groundwater, soft spots and over-excavation are not in it.
  • Sloping is geometry here, not a safety determination. Required slope depends on soil classification and the applicable excavation standard, and that call belongs to your competent person.
  • Bedding, pipe displacement and backfill are separate quantities. This calculates the excavation only.
  • Swell, density and truck capacity are yours to supply. There are no defaults, because published averages for them span ranges wide enough to change a haul budget by thousands.